View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Fixed duration - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Fixed duration

More
11 Fév 2016 10:39 #1 by El Wallos
Fixed duration was created by El Wallos
Hi

I tried to use the new (for me ;) ) mode planification "fixed duration", but I think I'm doing something wrong.

When I use it, it is not mandotory to fill work and assign it, is it correct? So, I just need to fill duration field, and after planning respect my duration.

But why this task is not displayed on my diary? And if it is normal, so it is not taking during this activity as a "work" so my diary is not real, because others activities could be planned on these days.

PD: I recalculated my planning but same thing, task is not displayed on my diary.

Thanks for your help

Please Connexion or Create an account to join the conversation.

More
11 Fév 2016 14:46 #2 by richard.pare
Replied by richard.pare on topic Fixed duration
Tasks are displayed on a diary for a resource.
So, if you are not specifying a resource to a task, it's normal that doesn't appear on any diary.
If you set "Fixed duration" and you assigned a resource to the task. The planning mode change to "As soon as possible". This not the behavior that do you want.
ProjeQtOr is oriented Effort-driven, so all features are available for this method.
I think "Fixed duration" should be used in the first draft of the project plan.

Please Connexion or Create an account to join the conversation.

More
11 Fév 2016 15:50 #3 by babynus
Replied by babynus on topic Fixed duration
Fixed duration can be used to trace "external" tasks : you know the duration but won't work on it.
Or for instance to add some delay between tasks :
Task 1 => paint wall (2 work days)
Task 2 => wait until paint is dry (5 days duration)
Task 3 => put paper on wall

If you put some work on fixed duration, work is planned regularly (like regular between dates but in a floating mode) and you'll then see it on diary.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
12 Fév 2016 13:08 #4 by El Wallos
Replied by El Wallos on topic Fixed duration
Thanks Babynus.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.034 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.