View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Regular in full days plans partial days - Page 2 - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Regular in full days plans partial days

More
12 Fév 2016 17:42 #7 by Guilhem
Yes, but even with "regular in full days", 0.1 days are planned :



Is there any reason why the planning calculation would to that ?
Attachments:

Please Connexion or Create an account to join the conversation.

More
12 Fév 2016 19:24 #8 by richard.pare
I tried your case on the test site.
So, I can change the planning mode and work distribution change too.
Have you recalculate the planning?

Please Connexion or Create an account to join the conversation.

More
12 Fév 2016 20:49 #9 by Guilhem
Yes I have recalculated the planning.

Seems weird to me, if I do a test on a newly created activity, it works well. But the issue appears on some projects, there must be something causing this, but I cannot see what exactly.

Please Connexion or Create an account to join the conversation.

More
12 Fév 2016 20:58 #10 by richard.pare
Me too, I don't know why. Maybe a bug. :(

Babynus help !

Please Connexion or Create an account to join the conversation.

More
13 Fév 2016 12:19 - 13 Fév 2016 12:20 #11 by babynus
Hi,

Very weird indeed.
I coumd not reproduce on first tests.
I checked code for unexpected assisnments (for instance if ($profile="REGUL") instead of if ($profile=="REGUL"), but found none.
So issue must be linked to scoecific use case.
Could you try and reproduce in the demo ?

(ticket #1971 recorded for analysis)

Babynus
Administrator of ProjeQtOr web site
Last edit: 13 Fév 2016 12:20 by babynus.

Please Connexion or Create an account to join the conversation.

More
13 Fév 2016 19:38 - 13 Fév 2016 19:39 #12 by Guilhem
Reproduced on demo :
Project : RegularFullDays
Resource : albert

Assigned 3 days "regular in full days" in february 2016



-> The issue appears when there is some real work already entered between the start and end date of the activity
(here I entered 1 day of administrative work on the 16 february)
Attachments:
Last edit: 13 Fév 2016 19:39 by Guilhem.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.058 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.