ProjeQtOr free project management software - Planning in hours - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Planning in hours

More
14 Fév 2016 14:45 #1 by bijugeo
Planning in hours was created by bijugeo
Hi...
Is it possible to enter planning in hours instead of days?
Thanks

Please Connexion or Create an account to join the conversation.

More
14 Fév 2016 15:53 #2 by babynus
Replied by babynus on topic Planning in hours
Yes.
Change unit in Global parameters.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
14 Fév 2016 16:30 #3 by bijugeo
Replied by bijugeo on topic Planning in hours
I changed it to hours in parameters. still in activity planning is in days.
Thanks
Attachments:

Please Connexion or Create an account to join the conversation.

More
14 Fév 2016 16:44 #4 by babynus
Replied by babynus on topic Planning in hours
duration is still in days (this will never change).
work is correctly in hours.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
14 Fév 2016 17:09 #5 by bijugeo
Replied by bijugeo on topic Planning in hours
My activities are of short duration... I dont want to club the activities together.
Any suggestions?

Please Connexion or Create an account to join the conversation.

More
14 Fév 2016 17:26 #6 by babynus
Replied by babynus on topic Planning in hours
Pay attention : planning very small activities (< 1 day) can be much time consuming.
You may spend more time planning activities than working on them...

But you can plan.
Duration will be 1 day (the smallest in ProjeQtOr) but work can be less.
(don't forget that projeqtor is work driven)
In that situation, you should take care to define "apply strict mode for dependencies" to false

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.039 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.