View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] Duration in planning mode - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

[SOLVED] Duration in planning mode

More
07 Mar 2016 16:38 #1 by DEngine
Hello!

I'm trying to plan my project. I have tasks, that contain 32 stages every. Some stages are longer than one day. But ProjeQtOr plans in other way. All stage (activity with type "task") have 1 day (as showed on printsreen). I want to see all plan. How have I change my plan in ProjeQtOr to see in ProjeQtOr activities durations what I want?

Can you help me?
Attachments:

Please Connexion or Create an account to join the conversation.

More
07 Mar 2016 20:37 #2 by Guilhem
Replied by Guilhem on topic Duration in planning mode
You must set the project workload in field "work" instead of field "duration".

Please Connexion or Create an account to join the conversation.

More
07 Mar 2016 20:42 #3 by DEngine
Replied by DEngine on topic Duration in planning mode

Guilhem wrote: You must set the project workload in field "work" instead of field "duration".


When? When do I plan?

Please Connexion or Create an account to join the conversation.

More
07 Mar 2016 21:01 #4 by DEngine
Replied by DEngine on topic Duration in planning mode
I tried. But ProjeQtOr recalculated and didn`t change planned duration. (see attached printscreen)
Attachments:

Please Connexion or Create an account to join the conversation.

More
07 Mar 2016 22:04 #5 by Guilhem
Replied by Guilhem on topic Duration in planning mode
Sorry : in fact you must assign those 31 days to your developer :

Attachments:
The following user(s) said Thank You: DEngine

Please Connexion or Create an account to join the conversation.

More
07 Mar 2016 22:24 #6 by DEngine
Replied by DEngine on topic Duration in planning mode
Thank You!

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.057 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.