View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] Does Projeqtor support Physical and Financial Progress comparison ? - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

[SOLVED] Does Projeqtor support Physical and Financial Progress comparison ?

More
17 Jui 2016 10:59 - 17 Jui 2016 23:12 #1 by keloniton
Hello Dear Mr babynus;
How are you? I have two questions about software.
1- Does Projeqtor support Physical and financial Progress comparison? As you know physical and financial progress are some of the main important matters which must be controlled during a project. I mean the amount we have paied and and amount we have progressed in project application. If Projeqtor does support it, how can i access it?
2- In activities, there are 4 fields, Validated, planned, Real, Requested. The Planned and Real are disabled for user data entering, How are they filled?
Thank you very much
Last edit: 17 Jui 2016 23:12 by keloniton.

Please Connexion or Create an account to join the conversation.

More
21 Jui 2016 15:59 #2 by babynus

1- Does Projeqtor support Physical and financial Progress comparison? As you know physical and financial progress are some of the main important matters which must be controlled during a project. I mean the amount we have paied and and amount we have progressed in project application. If Projeqtor does support it, how can i access it?

I don't know if this answers your question but you'll have several information of that kind in Project screen :
- expense and cost : is about all what you have spent (real expense, real cost)
- validated cost is what you have gained (may be computed from order item)
You also have report "project dashboard" the represent financial syunthesis of project.

2- In activities, there are 4 fields, Validated, planned, Real, Requested. The Planned and Real are disabled for user data entering, How are they filled?

Planned is calculated from planning calculation, taking into account work assigned and all constraints.
Real is defined from data entered in Real Work Allocation screen.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.032 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.