View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Employee Holidays summary in Resource Planning / or Serveral Months along with ongoing projects - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Employee Holidays summary in Resource Planning / or Serveral Months along with ongoing projects

More
22 Juil 2016 09:04 #1 by MohideenF
1. To get overview of Resource planning for Multiple projects and also their availablity like their Holidays, sick leaves etc.

I followed the previous forums and created a Admin project to enter the Off days in real work allocation. And then i see using coloured monthly resource
planning or may one month extra for off days and also extisting projects.. But i dont get complete overview of the reosurce planning for several months .

Is there a trick or tip where i can see the off days of team members in the Resource planning along with existing projects.

2.Second concern is.: how can i assign same resource , same task but different interval. Ex. Source A, Activity A in week 34 for 3 days, and then again in Week 35 for first two days. For Activitiy is it possible to give only one start and end date ?

Please Connexion or Create an account to join the conversation.

More
23 Juil 2016 13:51 #2 by babynus

Is there a trick or tip where i can see the off days of team members in the Resource planning along with existing projects.

No, not on current version

how can i assign same resource , same task but different interval. Ex. Source A, Activity A in week 34 for 3 days, and then again in Week 35 for first two days. For Activitiy is it possible to give only one start and end date ?

ProjeQtOr provides several ways to dispatch work over a period (% of assignment on activity, planning mode "regular between dates" or "fix duration") but all have regular dispatch mode. They cannot define different qunatity over time, wich you only know.
Only way is to enter real work in advance.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.046 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.