View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Proper understanding of "dates" related to activities, tasks, etc - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Proper understanding of "dates" related to activities, tasks, etc

More
30 Jui 2017 14:08 #1 by needhelp
I am having real problems understanding how the dates are functioning in the software; consequence is that I cannot close tasks and activities; for example:
I set an action on Monday - Initial due date: 26.June
I want to do it on Wednesday - Planned due date: 28 June; For whatever reason, I cannot take care of this action or I forget to mark it on the software; the status of the Activity is recorded;
Today Friday 30 June, I do all the operation
- allocate the activity to me ( handled:30.06) , then save
- mark the activity done ( done:30.06), save
After that, I want to close this activity, as it is DONE; and I have the error (red stamp with exclamation point - plus result window is marked with a red bar) Indicator: respect of planned due date !
After that, I started messing between accounts - user and Admin, hoping that I can force the closing of this activity but without any luck; I am messing the dates moving them back and forth but the error is still there . . . .
What am I doing wrong ? what is the proper way to proceed and how can I close / cancel some of the tasks, activities, etc without any pain ?

Please Connexion or Create an account to join the conversation.

More
30 Jui 2017 15:02 - 30 Jui 2017 15:03 #2 by needhelp
Sorry about that.
It seems to me that in order to be able to CLOSE an activity or a task, one should move the task or activity via entire chain of statuses ...from recorded to qualified, then to accepted / assigned / in progress . . etc . . .up to the CLOSED status.
After that, the only option one can have on a task/activity is to re-open !

What I actually did was to burn some of the steps, for example moving from recorded directly to assigned or directly to closed ! This seems to be not allowed.
Last edit: 30 Jui 2017 15:03 by needhelp.

Please Connexion or Create an account to join the conversation.

More
07 Juil 2017 15:59 #3 by babynus

After that, I want to close this activity, as it is DONE; and I have the error (red stamp with exclamation point - plus result window is marked with a red bar) Indicator: respect of planned due date !

Please post print screen.

What am I doing wrong ? what is the proper way to proceed and how can I close / cancel some of the tasks, activities, etc without any pain ?

Either you deal with status, moving item to status closed, or you can change behavior defined in Action Type, to unlock the "done" checkbox.
About status, check that workflow used (workflow used is defined in action type, workflows are defined in "Automation" section) allow current user (profile) to move to status done/

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.