Automatic calculation

More
28 Déc 2018 10:23 #1 by sogeti
Automatic calculation was created by sogeti
Hello,

I hope you had a great Christmas.

We have a problem with automatic calculatiion.

We put this parameters but the way ProjeQtor calculates the planning seems weird (we way not use it the good way).

It calculates old, closed and always the same projects (we can see it in the logs).

If we are not wrong, with the parameters we have chosen ProjeQtOr is supposed to calculate projects which have been modified the day of the new calculation.
Attachments:

Please Connexion or Create an account to join the conversation.

More
28 Déc 2018 11:13 #2 by babynus
Replied by babynus on topic Automatic calculation

If we are not wrong, with the parameters we have chosen ProjeQtOr is supposed to calculate projects which have been modified the day of the new calculation.

No, not only the day of the calculation : that has been changed since the last calculation.
There may be an issue with "closed" projets, that were not recalculated before closure : they may be considered as "to plan" but planning will not change them (as they are closed)

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
28 Déc 2018 16:31 #3 by sogeti
Replied by sogeti on topic Automatic calculation
Thank you for your answer but te problem is that we have created a new project to test automatic calculation but it didn't work. We have created a new project with an activity and a new activity in an existent project to test.

Do you have any idea where does the problem come from ?

Please Connexion or Create an account to join the conversation.

More
28 Déc 2018 16:44 #4 by babynus
Replied by babynus on topic Automatic calculation
Check on planning view : does icon of project has "orange" center ?
If not, you have to change things on activity (add assigned work)

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
03 Jan 2019 10:18 #5 by sogeti
Replied by sogeti on topic Automatic calculation
Hello,

The icon didn't have the orange center so I have modified the date of the activity to have it.
I have checked today but nothing happened. I don't have any calculation and the icon still have the orange center.

Please Connexion or Create an account to join the conversation.

More
03 Jan 2019 15:14 #6 by babynus
Replied by babynus on topic Automatic calculation
If the CRON process running ?
(check on admin page)

Do you have any trace on log file
(automatic planning generates a trace when starting)

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.