Resource end of contract

More
04 Mar 2019 12:11 #1 by timshel
Hi,
How can I mention the end date of a work contract of a resource ?
As not mentioned at the moment, the reports tell me that the resource is available in the availability report.
Best regards,
Tim

Please Connexion or Create an account to join the conversation.

More
04 Mar 2019 18:24 #2 by babynus
Replied by babynus on topic Resource end of contract
There is not such information.
Only allocation to projects can have a end date.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
04 Mar 2019 23:46 #3 by timshel
Replied by timshel on topic Resource end of contract
So can you confirm availibilty report doesn't reflect the truth ? Is it possible to have a new evolution request : had a field to insert the departure of an employee / staff member ?

babynus wrote: There is not such information.
Only allocation to projects can have a end date.

Please Connexion or Create an account to join the conversation.

More
05 Mar 2019 09:05 #4 by babynus
Replied by babynus on topic Resource end of contract
Request recorded as Ticket #3880

Babynus
Administrator of ProjeQtOr web site