View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Error planning calculation : unplanned work - Page 2 - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Error planning calculation : unplanned work

More
05 Jui 2019 15:39 #7 by babynus

How can I tell the planner that even if this project should occupy only 10% of the time of this resource, sometimes these meetings are prioritary over the other projects ?

You cannot bypass this constraint.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
05 Jui 2019 16:03 #8 by aleleve
Ok. I understand that I cannot bypass it.
Therefore, is there a way to know how to unblock this situation (I just know that these meetings are problematic) or to organize more efficiently my projects so that this kind of situation works ?

Typically, I organized in various projects my activities which correspond to different charges.
I created some project templates containing milestones, activities and meetings (by the way, I have to set a fake date to the meetings) which enable to plan efficiently new projects.
I have ~10 parallel projects in parallel with ~ 10% assigned to me each.
I imagine that a full day meeting in a project where I am assigned 10% worries the planner ?

Please Connexion or Create an account to join the conversation.

More
06 Jui 2019 17:58 #9 by babynus
No, you can manage it easily.
Just don't set restriction to allocation rate to project (set all at 100%).
Just set assignment rate to ensure you work at correct rate (10%) on each in parallel.
This way, meetings whould be correctly planned.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
07 Jui 2019 08:26 #10 by aleleve
Thanks for your quick answer.

Just to be sure I set the right parameters at the right place:

- in the resource page, I set every project rate at 100% even if it worries Projeqtor that the total amount of affectations is over 100%
- in the assignation of each task I put the real rate, say 10%

?

Please Connexion or Create an account to join the conversation.

More
07 Jui 2019 15:43 #11 by babynus
Yes

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: aleleve

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.045 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.