14 Mar 2019 09:56 #1 by QUANTAMEDICAL
We read that planification were based on multiple aspects :
  • Dependencies
  • Prioritized planning elements
  • Project priority
  • Task priority
  • WBS

Does the priority of a parent element have an impact on the planning calculation, if yes to what extent?

Thanks for your replies

Please Connexion or Create an account to join the conversation.

More
15 Mar 2019 09:11 #2 by babynus
No, priority of parent is not inherited.
It has no effect.