indicator "respect of the requested end date"

More
14 Mar 2019 10:01 #1 by QUANTAMEDICAL
Is the indicator of compliance with the requested end date compared with the actual date or the planned end date?

the comparison with the planned end date makes it possible to identify further upstream if the planning is coherent, whereas the comparison with today's date will too often be too late depending on the duration of the tasks involved.

Thanks for your replies

Please Connexion or Create an account to join the conversation.

More
15 Mar 2019 09:13 #2 by babynus
It is compared to actual date.