ProjeQtOr free project management software - Project cost update when 0 value is set - ProjeQtOr
 

Project cost update when 0 value is set

More
09 Avr 2019 14:56 #1 by ggoncalves
Hello,

It seems that the calculation of validated cost in the project is not updated if the validated cost of the activity is set to 0.

It works for other value. Is that normal?

Attached an image of an activity (cost 0 euro ) linked to a project (cost 1 euro, previous value set to the activity).

Thanks for the support
Attachments:

Please Connexion or Create an account to join the conversation.

More
09 Avr 2019 19:17 #2 by babynus

It works for other value. Is that normal?

It may be normal depending on global parameter "consolidate validated work & cost"
If set to "only if set", zero value is not consolidated.
If you need to consolidate zero, change parameter to "always"

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.028 seconds