11 Avr 2019 15:24 #1 by dep@eca.fr
Priority Project was created by dep@eca.fr
Is it normal that the priority on a planning of a project is not passed on to the subproject?

If I put a priority to 850 on project 1, and I do not touch the priorities of subprojects 1.1, 1.2, etc ...
During a planning calculation, the project 1 retreats well in time, but not the subprojects 1.1, 1.2, etc ...

I am obliged to apply the priority 850 to the project as well as all sub projects ... Is this normal?

Please Connexion or Create an account to join the conversation.

More
12 Avr 2019 00:14 #2 by babynus
Replied by babynus on topic Priority Project
Yes, priority is not inherited

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
12 Avr 2019 09:08 #3 by dep@eca.fr
Replied by dep@eca.fr on topic Priority Project
pity, it would simplify the planning calculation for us