View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Repport / Planning / synthesis of availability - Page 4 - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Repport / Planning / synthesis of availability

More
29 Avr 2019 14:26 #19 by babynus
Of course, planned work on the Pool can only use avalability of the resources of the pool that is not already used.
Sum of planned work for Poll + Resources can not be more than sum of availability for resources.

Let's take an example : You have 2 resources RA and RB, with capacity =1, taking part to a pool P.

RA is booked for the week : | 1.0 | 1.0 | 1.0 | 1.0 | 0,5 |
RA is booked for the week : | 1.0 | 0.5 | 0.5 | 0.0 | 0,0 |
P can be booked max to the week : | 0.0 | 0.5 | 0.5 | 1.0 | 1,5 |

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
29 Avr 2019 15:41 #20 by pipobru
thanks for your answer, but if you look the last line "Total" the sum of all affectations is 3 days but the maximum of the pool is 4. (i repet all ressources is only affected on the broject, without direct affectation, only via the pool).
Why the calculation don't use the full pool capacity ?

Please Connexion or Create an account to join the conversation.

More
02 Mai 2019 22:07 #21 by babynus
It won't use more than what resources can do.
Also when you assign pool to activities, you take part of pool capacity (for instance 1 FTE) so you may not use full pool capacity.
Also, you may have dependencies, planning modes, and so on, that will have resource not fully busy.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: pipobru

Please Connexion or Create an account to join the conversation.

More
07 Mai 2019 16:01 #22 by pipobru
Thanks,
I have create a test: New ressources, whitout other affectation, new ressources are in this pool "planification". All tasks are affected to the pool and only this pool. When i modify the pool with aditional ressource by aditional ressource, the result (after planning calcul) is coherent with 1, 2, 3 and 4 ETP, after the result is same (same for day planification and days available for the pool). I don't anderstand why numbers of days avaibale and planned days don't bouge after more 4 ETP. have you a limitation ? see the complete screens shots of all simulations in attachement.
Attachments:

Please Connexion or Create an account to join the conversation.

More
11 Mai 2019 16:56 #23 by babynus
Sorry, but seeing just availability result is not significant to me.
Could you please reproduce use case on Demo ?

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
13 Mai 2019 08:22 #24 by pipobru
Hello, Yes i can reprocuce with a online version.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.048 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.