Coloring of activities based on resources

More
22 Apr 2024 14:26 #1 by mckim
I'm having trouble understanding the behavior of the coloring of activities with respect to resource assignments. Specifically, activities are still showing as orange when I expect them to be green.

Here's my setup to demonstrate the behavior (my real-world case is more complicated with more resources and activities):
- 1 resource, assigned to the project at 100%.
- 2 activities, both set as Duration Driven because they must be completed during a certain timeframe. Duration is 7 days.
- The resource is assigned to both activities at a rate of 20%.

When I set the assigned days to the full duration (7 days) on both assignments, one activity is colored green on the Planning Gantt chart, and the other is colored orange. This does not seem correct, since the resource is only assigned for a total of 40%, less than the 100% allocation to the project.

When I change the assigned days to half the duration (3.5 days) on both assignments, both activities are colored green. This works whether the rate on the activity assignment is set to 50% or 100%.

I'd expect that in both these cases, both activities should be colored green.  Am I misunderstanding something?

 

Please Log in or Create an account to join the conversation.

More
27 Apr 2024 20:25 #2 by babynus

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
27 Apr 2024 21:35 #3 by mckim
Yes, I already read that section of the manual before I asked the question. Perhaps I should have stated that.

Why is one task getting colored green and the other orange? From what I can see, they are configured and assigned exactly the same.

Please Log in or Create an account to join the conversation.

More
28 Apr 2024 20:17 #4 by babynus
Orange means the planning requires some overbooking.
So the resource may be used on another task on same period
 

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.032 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.