I'm having trouble understanding the behavior of the coloring of activities with respect to resource assignments. Specifically, activities are still showing as orange when I expect them to be green.
Here's my setup to demonstrate the behavior (my real-world case is more complicated with more resources and activities):
- 1 resource, assigned to the project at 100%.
- 2 activities, both set as Duration Driven because they must be completed during a certain timeframe. Duration is 7 days.
- The resource is assigned to both activities at a rate of 20%.
When I set the assigned days to the full duration (7 days) on both assignments, one activity is colored green on the Planning Gantt chart, and the other is colored orange. This does not seem correct, since the resource is only assigned for a total of 40%, less than the 100% allocation to the project.
When I change the assigned days to half the duration (3.5 days) on both assignments, both activities are colored green. This works whether the rate on the activity assignment is set to 50% or 100%.
I'd expect that in both these cases, both activities should be colored green. Am I misunderstanding something?
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.