Good morning,
is it possible manage absence in "Real Work allocation"?
My problem is following:
there is an activity between 1 and 15 april assigned to a specific resource. This resource is absent on 10 april, so Planning is updated until 9 april despite has sumbitted untile 15 april. How can I do to manage this days?
I must add an activity "Absence"?
Create new Project "Out of work" (or else) with project type "Administrative".
Add activities as you with : "holidays", "sickness", "training", ...
Enter real work in the future on these tasks...
See attachments for green bar of Planning.
Resource in attachment file has not committed on 13 and 15 April (sickness) but Planning shows a filled green bar for those days. So I must see these days in Real Work Allocation.
Also I understand that in an Activity I must set only Validated Start Date and Assigned days for a Resource to view work percentage.
Thanks.
Th e grey line does not represent days where real work is entered.
The greay line represents the progress of the activitiy, in %. The lenght of the progress bar fills the activity bar proportionnaly to the progress.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.