I see it as a bug, but let me know if I am wrong : the planned date of a deliverable is only updated when associated with a milestone, not when the planning changes the date of the milestone. As a consequence, the planned date of the deliverables are very complicated to use (they are wrong most of the time).
Actually, from my experience, the expected behavior would be :
- if the milestone is a fixed one : the milestone forces the 'due date' of the deliverable, the planned date is what the project manager actually expects to happen.
- if the milestone is a floating one : the deliverable is a predecessor of the milestone, in this case the due date of the deliverable is the validated date of the milestone.
it works, I wrote too fast when answering before
I had the problem with 8.0.6 and wrote the message as I was updating our version to 8.1.8 (actually, when I wrote the message, I had a test version in 8.1.8 and a production version in 8.0.6 ... and I did not perform the test in the good window).
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.