We faced with issue from Timesheet: it seems planned work has been recorded automatically to all people assigned from january 1st, up to the end of the plan.
How can it be possible, how can we parameter that it never happens further?
By the way we still don't undestand how planned work displayed into timesheet is calculated. So we hide it. Values doesn't equal to the plan we think about. Could you explain us?
on global parameter, on automation does the "Automatic actual supply" field have the value "yes"?
The planned work displayed into timesheet corresponds to the planned work of a person on an Activity( or an other element), the unity for your timesheet it's the same as the unit of workload ?
Ok, so I keep it set "yes".
Into Global Parameter / Activity, there is "Manual Planned Interventions enter work as" : "planned" or "real". What does it mean and control?
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.