ProjeQtOr free project management software - Gantt display wrong in the duration bar - ProjeQtOr
 

Gantt display wrong in the duration bar

More
22 Mar 2021 18:55 #1 by j.buquet
Hi,

Something strange :
- If I charge 5 days on a task without assigning some days to a ressource, the bar is OK with 5 days
- With the same task, if I assign 5 days on one ressource, the bar is reduced at 1 day

Projeqtor 9.0.2
Attachments:

Please Log in or Create an account to join the conversation.

More
24 Mar 2021 12:50 #2 by Arkhanje
Hello,

First of all, I want to let you know that you are working on a version that has never been tagged stable. First, consider upgrading to version 9.0.6.
Maybe the problem will be solved after this.

If not, remember to check if your activity is not paused, it cannot be seen in your screenshot.
Otherwise, check the capacity of your resource, if its FTE is> = 5 then it will do what it was assigned to in 1 working day.

Do not hesitate to come back to us if the problem persists!
Good continuation

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.051 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.