ProjeQtOr free project management software - Issue when running the planning with "fixed duration" and dependencies - ProjeQtOr
 
 

Issue when running the planning with "fixed duration" and dependencies

More
17 Nov 2021 17:14 - 17 Nov 2021 17:15 #1 by BaptisteAW
Hello,

I'm planning activities with "fixed duration", I add a dependency "end-start" so it postpone the start of the next activity to the end.
And when I run the planning it put the activity on the past without reason. The activity is assigned, only parameters/constraints are the fixed duration of 10 days and dependency end-start. See screenshots attached.

Thank you for your help.
 
Attachments:
Last edit: 17 Nov 2021 17:15 by BaptisteAW.

Please Log in or Create an account to join the conversation.

More
22 Nov 2021 20:37 #2 by babynus
I cannot reproduce.
Are you sure that both tasks are "Fix duration" ?

Please try and reproduce on Demo.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
24 Nov 2021 13:08 - 24 Nov 2021 13:09 #3 by BaptisteAW
I cannot reproduce too.
But on this project I cannot explain why it is doing this.
Have you a way to have a look on our ProjeQtOr instance ?
The Project is the following, and the two activities are at the bottom of the screenshot.

 

Thank you
Attachments:
Last edit: 24 Nov 2021 13:09 by BaptisteAW.

Please Log in or Create an account to join the conversation.

More
25 Nov 2021 09:43 - 25 Nov 2021 09:43 #4 by babynus
It seems the parent activity 3.7.8 has a dependency with upper activity 3.7.7.
As it it drawn, I guess it is a end-end dependency.
Can you try and remove it ?

Babynus
Administrator of ProjeQtOr web site
Last edit: 25 Nov 2021 09:43 by babynus.

Please Log in or Create an account to join the conversation.

More
25 Nov 2021 09:50 #5 by BaptisteAW
Thank you that solved the issue.

But I don't understand why it works like this ?
Because for me this dependency is a constraint which prevent 3.7.8 to finish before 3.7.7. So I dont understand why it has an impact on this.

Thank you

Please Log in or Create an account to join the conversation.

More
25 Nov 2021 11:23 #6 by babynus
Hi,

It is a restriction of ProjeQtOr, which does not really manage "backward" planning.
When you set an end-end dependency from predecessor X to a parent activity P, all the activities (A and B) on the parent get the dependency, and this will "remove" internal end-start dependencies.
What you may do is define end-end dependency from prececesor to last activity under the parent activity (from X to B).
But I gess you won't really get what you expect as predecessor of last actity (A) will be planned ASAP, and not The Latest possible to fit the end-start dependency. 
This is because of unavalability of "reverse planning mode" (what you expect is some reverse planning inside the parent activity)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.054 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.