I just installed Project'o ria, eveything seems to work except this :
I create tasks with links (predecessor and successor), but the Gantt diagram does'nt take care of the links after calculation. The tasks appear to be linked, but for example the successor task remains before the successor.
Is there something I missed ???
What you get may happen if you define some planning mode based on work (for instance "as soon aspossible, wich is the default one) and you don't define any work : just try and define assignements to the tasks (activities) and set some assigned work, it should work better.
Or maybe you'd prefer define tasks as fixed duration...
Thanks, babynus, it works better now.
This tool is very complete, but a little bit difficult to use at the beginning (I was working with Open workbench before, which is nomore developped now).
Regards,
Jean-Jacques.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.