User must have rights to enter real work for the corresponding resource.
Check if the user has the hability to enter real work for this resource on the timesheet screen.
Hi, I finaly manage to acheive manuel planing for an activity.
My Profile was not one of the predefined profiles. So I had to swap to a predefined profile to acces this planning mode.
Now, I'm facing a strange issue. Even if I delete planned tasks on the calendar view, An occurence is still present in the agenda View at a date corresponding to the end planned ate of the activity.
Even if I calculate the planning, this task still present in the agenda View.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.