[SOLVED] project priorities troubles

More
05 Oct 2023 15:32 #1 by loicr
Dear all,

On specific project, to change priority, we put project at 700 instead of 500 but all tasks are planned before project with activities at 500.

I don't understand what happen. It seems that priorities are not taken into account. ( we also move project to have lower wbs : no change ... )

We put also subtask and sub activities at 700 but result is the same, after new calculation, the task is done as soon as possible despite other projects.

i've put project in pause to avoid the tasks to be planned before others.

Sincerely

LR

ps: Projector V11.0.0 with mysql on ubuntu 22 php 8.1

Please Log in or Create an account to join the conversation.

More
09 Oct 2023 19:05 #2 by babynus
Replied by babynus on topic project priorities troubles
Planning priorities depend on several factors, includng planning mode.
Have a look at user manual for more information.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
10 Oct 2023 11:43 #3 by loicr
Replied by loicr on topic project priorities troubles
Thanks a lot, i've got planning end date priority check in global parameter !

Thanks
LR

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.042 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.