On specific project, to change priority, we put project at 700 instead of 500 but all tasks are planned before project with activities at 500.
I don't understand what happen. It seems that priorities are not taken into account. ( we also move project to have lower wbs : no change ... )
We put also subtask and sub activities at 700 but result is the same, after new calculation, the task is done as soon as possible despite other projects.
i've put project in pause to avoid the tasks to be planned before others.
Sincerely
LR
ps: Projector V11.0.0 with mysql on ubuntu 22 php 8.1
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.