The resource François is used as an individual resource and in the Dev pool, as most of the resources. But in the workload report, it is duplicated cf screenshot. The workload itself is different. It would be nice to have the resource ID in a column to better understand what may happen. And then to be able to fusion them. Only one François is assigned to the project.
There is one François created as a resource first to perform assignment to activities, then later an account has been created for this François in order to access ProjeQtOr. But this last François is not used for assignments.
There is only one project.
Enclosed : view of resources showing two François (and also two Franck), detailed view of François id 10 showing his assignment to the project, detailed view of François id 46 showing he is not assigned to anyproject.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.