2 tasks - first is predecessor fo the second and both set to be as soon as possible:
XXXXXXXXXXXX - 1st
XXXXXXXXXXXXX - 2nd
if task 1 moved the second suppose to move as well, so we would expect:
XXXXXXXXXXXXX
XXXXXXXXXXXXXXXX
but instead we are getting:
XXXXXXXXXXXXX
XXXXXXXXXXXXX
Regards,
Evgueni
But, to be sure, there are several constraints :
- you must re-calculate planning each time.
- this will correctly work for "as soon as possible tasks" only if some work is assigned (left work must exist)
- if task 2 has some real work, then it begins at find real work day, no matter the constraints (as it is some reallity, it overrides all planning constraints)
Hi,
What is the lenght of overflow ?
Only one day or more ?
One day overflow can be normal : planning is correct and first task ends on one day, second starts the same day, just after.
Is this this case or do you face more complex issue ?
It is unpredictable. In some cases (projects) assigning work left hours will work OK but in some it still will create a mess...
It will be good to have an export available to send you some of this projects to look at
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.