ProjeQtOr free project management software - Anomalies under Global Planning screen - ProjeQtOr
 

Anomalies under Global Planning screen

More
12 Sep 2024 15:34 #1 by lumit
Hi, here is what happens to me (v.11.3.2 but also in the previous one).

1)  The bar color of "Duration Constrained" activity  (and only for this type of activity) on  Global Planning Gantt becomes red as soon as the activity is created and always remains red. This does not happen on Planning screen Gantt, where, correctly, the bar of same activity is green after creation.

2)  Columns layout modify:  go on "Select columns to display" form for changing number and order of columns -> Manage -> when I click on "Attribute" button after creating the layout (for propagation to all users) I get the following: ERROR on file '/var/www/html/tool/dynamicDialogLayoutForOthers.php' at line (35). Cause = Undefined array key "Planning". Sometimes there is no error (I did not understand why)  but in any case  pressing on OK has no effect on  Global planning layout of other users. This does not happen under all other screens (Planning, Projects, Activities, Meeting, Actions, ...),   when columns layout propagation works by "Select columns to display" form.
I tried to restart application, reset columns layout to default configuration, but nothing to do. 
(P.S. Instead, Resetting layout solve another problem also had  2 times on Project screen: all data suddenly disappears on report-table, remaining only the header with the names of the fields !  I think this can happen following too many changes to number and order of the fields displayed)
 

Please Log in or Create an account to join the conversation.

More
12 Sep 2024 17:00 #2 by lumit
I forgot,  don't know if this is also an anomaly:

3)  Display of the numerous elements on the Global Planning screen would be better if they were all nested under the project they belong to: unlike the activities, meetings and milestones (i.e. the elements that appear on the Planning screen), the other elements, such as the Actions, are subsequent at WBS level but are not nested under the project, and this for me creates a lot of confusion observing the long list of items, almost as if they were other projects.

Thank for attention

Please Log in or Create an account to join the conversation.

More
16 Sep 2024 09:09 - 16 Sep 2024 09:10 #3 by Arkhanje
Hello 

The bar color of "Duration Constrained" activity  (and only for this type of activity) on  Global Planning Gantt becomes red as soon as the activity is created and always remains red. This does not happen on Planning screen Gantt, where, correctly, the bar of same activity is green after creation.


It is very complicated to explain what can happen without other information. Can you capture the details of this activity on both schedules (with a maximum of details: dates, load, is the resource shared...?) because on our side, we do not reproduce.

2)  Columns layout modify...


Same, we don't reproduce. Can you attach the projeqtor logs? Do you have any error messages in the browser console?

3) L'affichage des nombreux éléments sur l'écran de planification globale serait meilleur... 

Recorded! One day, if we have a sponsorship to make it happen, why not, in the meantime, you can change their place manually!
Last edit: 16 Sep 2024 09:10 by Arkhanje.

Please Log in or Create an account to join the conversation.

More
16 Sep 2024 17:10 - 18 Sep 2024 09:41 #4 by lumit

 Arkhanje post=37851 wrote: Hello 

The bar color of "Duration Constrained" activity  (and only for this type of activity) on  Global Planning Gantt becomes red as soon as the activity is created and always remains red. This does not happen on Planning screen Gantt, where, correctly, the bar of same activity is green after creation.

It is very complicated to explain what can happen without other information. Can you capture the details of this activity on both schedules (with a maximum of details: dates, load, is the resource shared...?) because on our side, we do not reproduce.For comparison test on different planning mode, I had created and recreated in these days  some very very simple activities with only the bare minimum of parameters: Name, activity type, validated Start date, validated End date, Validated workplanning Mode, and no other parameters !  I attach Gantt of Planning and Global planning screens., with visualized only the last 3 activities (and  Progress tab  of Constrained activity at the bottom)  having different  only the planning mode, that is in order: Fixed, Driven and Constrained duration  Task. As you can see from the screenshot  on Global planning screen  the bar of Constrained activity is red and  became red immediately, as soon as it was created with the aforementioned parameters. Instead its color appears green on Planning screen,  and I  think it should  have been also green on the Global screen.

2)  Columns layout modify...

Same, we don't reproduce. Can you attach the projeqtor logs? Do you have any error messages in the browser console?Error message in the log file is the one I reported.  I attach screenshots of the latest log records reporting that error and also the message in the browser console..   I emphasize the fact that even the rare times in which this error message did not appear, in any case  layout of other users not changed  according changes made by the administrator.  Does layout propagation work for you on Global Planning screen  ?!

3) L'affichage des nombreux éléments sur l'écran de planification globale serait meilleur... 

Recorded! One day, if we have a sponsorship to make it happen, why not, in the meantime, you can change their place manually!P.S.  I am paying close attention to the anomalies on the Global screen (or at least, anomalies that I notice on my  ProjeQtor dockerized instance), because in my opinion it is very useful and convenient. Usually, once logged in ProjeQtor I position myself on the Dashboard for monitoring and then on the Global Planning for  management and creation of  all elements, considering the Global planning screen allows a global view of all project's elements and to create immediate "any" item with just a button, without going to dedicated menù 

Last edit: 18 Sep 2024 09:41 by lumit. Reason: Excuse me, I've added missing attachment from yesterday and 2 new one from today

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.039 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.