I think it might be when assigned(d) is 0. It is not shown for that resource, even if it is assigned. Is this how it is supposed to be (Maybe it just worked accidentally in < 11.4 when using the initial view?) ? Is there a way to show it anyway?
indeed if the assigned load is 0, it is because this resource is not planned on the project activities and seeing a non-existent planning on a planning tool will be complicated...
It must be remembered that the assignment on the project gives a set of raw rights on the project, the assignment on the activity is to distribute work. No work no display.
Is there a way to show it anyway?
What exactly do you want to see if not the load? the list of resources on the project?
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.