16 Dec 2024 15:27 #1 by jmmbb
Hello,

i'm trying to set state when activity is assign.
I change global parameter "Status change on assignment" to YES.

I use following status :
 

I want to assign activty in "accepté" status :
 

But, when using "Assign to me" (the same if i choose resource from combobox and save activity), i get no change on status :
 

Thanks for advice.

regards,
 
Attachments:

Please Log in or Create an account to join the conversation.

More
17 Dec 2024 09:36 #2 by Arkhanje
Hello
So, the global parameter "change status on assignment" is done on... drum roll! an assignment! 
There you inform the person responsible for an element.
Try to assign a resource on your activity and the status will automatically change to the one that will mark the first, "assigned status"
In your case (screenshot attached), this will be the assigned status.

Please Log in or Create an account to join the conversation.

More
19 Dec 2024 11:03 #3 by jmmbb
Hello,
With parameter "auto assign responsible to activity", it works :
- setting responsable lead to make an assignment for responsable
- auto setting of assignment lead to set status to "assigned".

Thanks !

Please Log in or Create an account to join the conversation.

More
19 Dec 2024 11:22 #4 by jmmbb
Strange, in test for another activity and auto assignment doesn't work anymore...

First, activity is set to "Accepté" according to the workflow.
 

Second, i set responsable :
 

Note that there is no assignment, even with global parameter "auto assign responsible to activity" set to "yes" :
 

And i can reproduce good behaviour only with new activity (not with one where assignment where deleted).

I find the issue : for planning mode "fixed duration", there is no auto assignment, so status can't change !

Is it possible that, for fixed duration, status can be change even if there is no assignment ? I understand that there is no assignment because there is no work element for fixed duration and manual advancement set, but it leads to no intuitive behaviour for users.

Regards,
Attachments:

Please Log in or Create an account to join the conversation.

More
20 Dec 2024 20:17 #5 by babynus

I find the issue : for planning mode "fixed duration", there is no auto assignment, so status can't change !

Is it possible that, for fixed duration, status can be change even if there is no assignment ? I understand that there is no assignment because there is no work element for fixed duration and manual advancement set, but it leads to no intuitive behaviour for users.

Exactly : assignment is not created for "fix duration" (and "Constrained duration" and "Duration driven") because this planning mode does not expect to have work.
If we create an assignement for fix duration, the Manual Progress will not work any more, as for manual progress activity may have responsible but cannot have assignment.

Optionnaly, we could created assignement for fix duration if global parameter for Manual Progress is set to No

 

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.089 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.