ProjeQtOr free project management software - Gantt chart - late as possible planning - ProjeQtOr
 

Gantt chart - late as possible planning

More
22 Mar 2012 13:00 #1 by ekolossov
Gantt chart - late as possible planning is not working. For task we have set end date and duration but task just not shown in Gantt chart even after recalculation

Please Log in or Create an account to join the conversation.

More
22 Mar 2012 13:33 #2 by babynus
To be calculated, task must have some work (left work > 0)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
22 Mar 2012 13:59 #3 by ekolossov
Thanks - it works!

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.049 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.