04 Apr 2012 15:12 #1 by climb4fun
Hi Babynus,


once you save an item, then indicator will check and send Warning or Alert. That's good.


But if on due date, a task is set to done / closed -> done = 1 and/or closed = 1, then it should not check indicators.



Klaus

Please Log in or Create an account to join the conversation.

More
04 Apr 2012 15:50 #2 by babynus
Indicators are designed to work the way you describe it.
If it does not, it-s a bug.
I registered the issue as ticket #623.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.066 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.