Maybe I've done some wrong costs assignements, but when I compare the following reports:
resources costs per month and cost synthesis per activity, the second is correct while the first is overestimated.
I don't know how to provide an example, but you can try at your level if it's the case.
I have the explanation of differences :
- "cost synthesis per activity" retreives costs from activities (real and left) : it is always up to date
- "resource cost per month" retreives data from planning : real costs, months by months, as entered by reosurces, and left work, months by months, as planned by Planning process.
If left work is updated on some tasks, these two reports will display differences, as long as planning is not run again.
Run planning calculation will resync "planned" and "real" values.
It works. Well understood.
Thank you very much, now I understand better how the planning works and where do i have to perform corrections when plans changes.
I would like to create some custom reports, is there any documentation to allow me to avoid doing stupid errors on this?
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.