14 Feb 2013 11:26 #1 by climb4fun
Hi Babynus,

we introduced multiple assignments of team members to activities.

Example:

John Doe is assigned as Manager and Functional Analyst and Developer - see screenshot below.



If he now will enter his real work then he got this list displayed - see screenshot below:


The issue: He is not able to distinguish between his different assigned functions, because this level of information is not provided.

Possible solution: add a column with details from assignment - i.e. function.

Regards,

Klaus
Attachments:

Please Log in or Create an account to join the conversation.

More
14 Feb 2013 13:03 #2 by babynus
Right !
Recorded as ticket #1002

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.045 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.