ProjeQtOr free project management software - item in real work allocation gone after trying to close an activity - ProjeQtOr
 
 

item in real work allocation gone after trying to close an activity

More
08 Jul 2011 09:41 #1 by Guest
Hi,

I have a question about the activity.
I created an activity with two work assignments to 2 persons.
After one person A completed the assignment and inserted in real work allocation with left work = 0.
B didn't complete the assignment yet.
I then changed the activity status to 'done' w/o problem.
Then I tried to change again the activity to 'closed' but failed. It showed 'Unable to close an element with left work'.
So far, it is correct.
Then, B needs to insert some work hour to let the left work = 0, but that assignement in B's real work allocation page is gone.
Though that assignment in A's real work allocation still exists. The activity's status remained in 'done' status.
B can never insert work hour and the activity can never be closed.

Please help to check.
Thanks a lot.

Best Regards,
Selina

Please Log in or Create an account to join the conversation.

More
08 Jul 2011 09:45 #2 by Guest

Selina wrote: Hi,

I have a question about the activity.
I created an activity with two work assignments to 2 persons.
After one person A completed the assignment and inserted in real work allocation with left work = 0.
B didn't complete the assignment yet.
I then changed the activity status to 'done' w/o problem.
Then I tried to change again the activity to 'closed' but failed. It showed 'Unable to close an element with left work'.
So far, it is correct.
Then, B needs to insert some work hour to let the left work = 0, but that assignement in B's real work allocation page is gone.
Though that assignment in A's real work allocation still exists. The activity's status remained in 'done' status.
B can never insert work hour and the activity can never be closed.

Please help to check.
Thanks a lot.

Best Regards,
Selina

BTW, the version is 1.5.5.
Oh. It seems that if the status of the activity is done, even though the assignment is not done, in B's today page, that item is not shown.
B may forget this assignment forever.

Best Regards,
Selina

Please Log in or Create an account to join the conversation.

More
08 Jul 2011 10:03 #3 by Guest

Selina wrote:

Selina wrote: Hi,

I have a question about the activity.
I created an activity with two work assignments to 2 persons.
After one person A completed the assignment and inserted in real work allocation with left work = 0.
B didn't complete the assignment yet.
I then changed the activity status to 'done' w/o problem.
Then I tried to change again the activity to 'closed' but failed. It showed 'Unable to close an element with left work'.
So far, it is correct.
Then, B needs to insert some work hour to let the left work = 0, but that assignement in B's real work allocation page is gone.
Though that assignment in A's real work allocation still exists. The activity's status remained in 'done' status.
B can never insert work hour and the activity can never be closed.

Please help to check.
Thanks a lot.

Best Regards,
Selina

BTW, the version is 1.5.5.
Oh. It seems that if the status of the activity is done, even though the assignment is not done, in B's today page, that item is not shown.
B may forget this assignment forever.

Best Regards,
Selina

Sorry, I just had another question after this operation of activity.
After I assign the activity to 2 persons.
I change the project (ex. ooo) to another project ( ex. xxx), I found in A & B's real work allocation page, the activity/assignment is still put under ooo instead of xxx.
I tried to disconnect and relogin, the position is still the same.
Please also help to check.

Thanks a lot.

Best Regards,
Selina

Please Log in or Create an account to join the conversation.

More
12 Jul 2011 22:33 #4 by babynus
First issue registered as #356
Second as #357
under analysis

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
13 Jul 2011 20:28 #5 by babynus
Issue #356 fixed for V1.6.1.
To retrieve assignment in real work allocation :
- note the id of activity
- fetch on database (with tool such as phpmyadmin) assignments with this activity and set idle to 0 (zero).

Regards
Babynus.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.035 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.