View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Support us on Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - BUG - Can't update (or) change project affectation resources. - ProjeQtOr
 
 

BUG - Can't update (or) change project affectation resources.

More
19 Jul 2011 13:37 - 19 Jul 2011 13:38 #1 by stevanovich
Hi,
I woul'd like to change a % of project afffectation ressource (user), because i can't set this user to another project.
This user also use real work allocation .
When i change affectation of this user, in an activity , % inside activity is updated, but % inside project is not updated and seem to still locked to 100%
I can't delete this user from this activity (because of real work allocation ?).
So now i cannot set this user to another activity.

Hope i explain it correctly ... (i must improve my english ;-) )
Best regards.

Stéphan.

Please Log in or Create an account to join the conversation.

More
19 Jul 2011 14:06 #2 by stevanovich
Sorry,
I found what was the problem, not a bug !!!
I must unset or change the % of use in Affectation (Environnement)
After, i can now set this user to an other project.

I am glad to discover that i must set user affectation in environnement to be able to set user activity ....
Should'nt be better to be able directly assign user affectation in activity ?

Thanks

Please Log in or Create an account to join the conversation.

More
19 Jul 2011 17:52 #3 by babynus
Hi,

All of this is clerly eplained in the online manual (on Planning part) :

A resource has a capacity
Most of the time Capacity = 1 FTE (1 full time equivalent), but it may be more (if the resource is not a person but a team) or less (if the person work only partial time).

A resource is affected to a project, at a certain rate
If resources are not shared between projects, so rate will probably always be 100%.
But if resources are shared, then rate could be less than 100%. If a resource is equally shared between two projects, then each project should enter a rate of 50%. This will lead to control that planning for each project will not overtake rate capacity, so that first project planning its activity will not take all the availability of the resource.
Project affectation capacity is controlled on a weekly basis. This means that planning for a project (including sub-projects) will not be more than (Resource Capacity) x (Resource affectation rate) x 5 for a given week.

A resource is assigned to an activity, at a certain rate
By default, assignment rate is 100%. But it may be less. This means that planning will keep some availability for other tasks.
Assignment capacity is controlled on a daily basis. This means that planning for an activity will not be more than (Resource Capacity) x (Resource assignment rate) for a given day.

This is not the most simple way, but it is the most able to fit all needs.

Regards.
Babynus.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.051 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.