Closing activities will reduce parent activity2

More
12 Mar 2014 18:06 #1 by jmmbb
Hello,

when i use "close" for an activity to make it to disapear from real work table, parent activity is reduce as if closed activity not exist (even if i use "show closed items").

I attach a screen copy to help you undesstand my poor english :( !
.

Please Log in or Create an account to join the conversation.

More
12 Mar 2014 23:43 #2 by babynus
Sorry, I don't understand,
and screen copy is not attached :(

Here are few questions to try and understand :
- What do you mean by "close" the activity : set it to a closed status ? With closed status checkbox checked ?
- What do you mean by : parent is reduced ?
- IS the resource assigned to both activities, parent and closed one ?

My test is :
Activity 1
Activity 1.1
Resource R is assigned to Activity 1.1.
=> On real work for R, I see 1 and 1.1.
Then I close 1.1.
=> On real work for R, I do not see 1 and 1.1 anymore.
Then I assign R to 1
=> On real work for R, I see 1.
=> only strange behavior, is that I have a cross to expand Activity 1, and when I click on it, it expands to ... nothing. This ios due to the fact that 1.1 exists, even if not displayed.
If I select "show closed"
=> I see 1 and 1.1
All seems correct to me.

Please describe complete test and what you expect.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
13 Mar 2014 08:32 #3 by jmmbb
Sorry, i attempt a new attachment...

Close activity : closed checked with date
Parent reduced : I meen that, in Gantt, you will see parent activity size decrease according to status of dependant activity, even if you ask for viewing closed ones.
Ressource is or not assigned to parent

Regards,
Attachments:

Please Log in or Create an account to join the conversation.

More
13 Mar 2014 11:22 #4 by babynus
Hi,

If and can reformulate the description.
You have 1 parent activity (1) with 2 (at least) sub-activities (1.1 and 1.2).
When you plan, parent longs from start of 1.1 to end of 1.2.
If you close activity 1.1, then parent activity 1 longs from start of 1.2 to end of 1.2, as if 1.1 do not exist any more.
This occurs even if you display 1.1 (using show closed activity) : this way, you see 1.1 starting before start of parent 1.

Is that correct ?
On which version of ProjeQtOr did you face this issue ?

For information, I tried it on V4.2.1, and all was correct (on following print screen, activity 6.2.1.1 is closed)





Babynus
Administrator of ProjeQtOr web site
Attachments:

Please Log in or Create an account to join the conversation.

More
13 Mar 2014 13:45 #5 by jmmbb
Youre correct, this is exactly the problem.

We are in V 4.1.2 actually.

Please Log in or Create an account to join the conversation.

More
13 Mar 2014 14:01 #6 by babynus
OK, I'll try and repproduce.
It should be linked to specific situation.

Ticket #1331 recorded.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.060 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.