I use projeqtor 4.1.2 and setup a per resource calendar. When I set days off on the default calendar and go to imputation page, the days off are marked grey and that's fine, but when I do the same on a resource calendar, the imputation page does not change. Is it an issue or is there a way to really attach resource imputation to its calendar ?
Adding an off day in the defualt calendar do not include it automatically into all others calendars.
You have to manually import default calendar into each calendar. Fortunately, there is a button to do this.
You're right Stephane,
Only defaut calendar is taken into account to display off days.
It is OK for planning (where multiple resouces are concerned), but on real work allocation, calendar taken into account should be the one linked to the resource.
Ticket #1335 recorded
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.