I have an issue with cancelled activity. It's possible to cancel an activity even this activity is linked to assignment with real work. I think it's a functional bug, it should be impossible to cancel an activity where somebody have record activity ? do you agree with that ?
The problem is for reporting purpose, the activity is cancelled but with work imputation !
No it is not a bug.
It often happens that you start to work on an activity that is cancelled.
For instance, first work shows impossibility to get expected result, or for work is juste estimation of activity.
Then, you can have real work on cancelled activity.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.