I don't know if it's an issue or if you have an explanation for this but total for assigned and reassessed should be 171 d (on screenshot), why is it 175 d and 174,5d?
Assigned can be different from validated.
I don't see all lines, so cannot sum up all assigned.
For re-assessed, it is always real+left : so calculation seems correct.
1) First I did not see that last lines are not summed up on the parent task above (grey line). If is surely because they are directly under the project.
2) If after deletion you still have assigned work, I may be because you have a closed activity. Try and display activiites with "show closed" checkbox checked.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.