[SOLVED] "Not planned work" is not updated

More
05 Dec 2015 16:38 #1 by stephane.pelletier
Hi,

When work can no be planned on an activity; information is displayed in red in the assignement of adequate resource (number of days / hours that could not be planned).
However when I change the assigned work to the same resource and that I assign a correct effort (correct in the sense it could be allocated in the timeframe for this resource) and re-calculate the planning for the project / activity, the information on overallocation remains the same.

I have created example on demo site => Project "Project for issue on non planned work" / Activity "Task #1". (see attached screen shot)

Thanks
Stephane Pelletier
Attachments:

Please Log in or Create an account to join the conversation.

More
06 Dec 2015 17:51 #2 by babynus
Issue confirmed : "not planned work" is not updated if there is not left work.
For information, I tried setting left work = 0,1 : the not planned work is then updated; but still with not planned work = left work as the resource has no availability...

Ticket #1886 recorded

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.030 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.