When work can no be planned on an activity; information is displayed in red in the assignement of adequate resource (number of days / hours that could not be planned).
However when I change the assigned work to the same resource and that I assign a correct effort (correct in the sense it could be allocated in the timeframe for this resource) and re-calculate the planning for the project / activity, the information on overallocation remains the same.
I have created example on demo site => Project "Project for issue on non planned work" / Activity "Task #1". (see attached screen shot)
Issue confirmed : "not planned work" is not updated if there is not left work.
For information, I tried setting left work = 0,1 : the not planned work is then updated; but still with not planned work = left work as the resource has no availability...
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.