Planning Problem

More
14 Dec 2015 10:57 #1 by El Wallos
Planning Problem was created by El Wallos
Hi

Today, I plan a task with a work but I was surprised about the planning, this task was planned for last friday. How is it possible if the task is created today? Why the planified date is 11Dic2015?

I changed the requested date to see the impact but nothing is done, what is the goal of the requested date field?

Thanks
Attachments:

Please Log in or Create an account to join the conversation.

More
14 Dec 2015 20:52 #2 by babynus
Replied by babynus on topic Planning Problem
There in no impossibility to plan a task before current day.
Requested date has no effect on planning : it is only informative.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
15 Dec 2015 09:16 #3 by El Wallos
Replied by El Wallos on topic Planning Problem

babynus wrote: There in no impossibility to plan a task before current day.


But if I'm creating the task today, I didn't work on this task last friday so the task is late before begin it. :blush:

I don't understand in which case is useful plan a task before current day?

Please Log in or Create an account to join the conversation.

More
15 Dec 2015 18:52 #4 by babynus
Replied by babynus on topic Planning Problem
If you define a task that can have been worked on by resource during current week, it may be usefull to plann it fro real start day (and not from current day) if you know that resource has not entere d real work yet.
Now it is just a possibility.
If you ru pllanning calculation with stating date ) today, you won't have this behavior.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
16 Dec 2015 09:58 #5 by El Wallos
Replied by El Wallos on topic Planning Problem
Thanks for the clarification.

If I define a starting date with ASAP planification mode, the starting date is just an indication to plan (ie at least the task should be begin at the starting date, but it is possible to plan after depends of priority and disponibility of ressources).

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.037 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.