ProjeQtOr free project management software - [SOLVED] Real work allocation - Bad allocation after input - ProjeQtOr
 
 

[SOLVED] Real work allocation - Bad allocation after input

More
19 Aug 2016 13:19 #1 by fredparis
Hi Babynus,

Something strange that happends for the first time since I use ProjeQtOr (since 2011, october).
In Real work allocation screen, when I write 0.25 and save it, that is correct. The sum of the day is 1.



But after refreshing the screen, the value is changed to 0.5 and the sum of the day is 1.25, which is wrong.



How is it possible ?
I try to correct this value, but even after saving, submitting, validating work, it's always change to 0.5.
I don't understand...

Do you have an idea ?
Thanks
Fred
Attachments:

Please Log in or Create an account to join the conversation.

More
19 Aug 2016 14:22 #2 by babynus
I cannot reproduce on V5.4.4.

Which version are you using ?

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
19 Aug 2016 14:57 #3 by fredparis
Hi,
I'm on V 5.4.4

Please Log in or Create an account to join the conversation.

More
19 Aug 2016 15:03 - 19 Aug 2016 17:30 #4 by fredparis
If that can help, here is the main screen of this activity :
Attachments:
Last edit: 19 Aug 2016 17:30 by fredparis.

Please Log in or Create an account to join the conversation.

More
19 Aug 2016 19:19 #5 by fredparis
Hi,
I think my way to use ProjeQtOr is not quite correct.
- I use only 1 project : the "master" project. And then, I use activities.
- Since 2 weeks, I use sub-activities to be more precise. But it works bad with real work allocation screen : sub-activities does not report the total in their "master-activities" allocation line.

So I will change my way :
- rather than activities, I will use sub-projects.
- then sub-activites become activities. I think it will be more correct.
And perhaps, the real work allocation screen will work more properly than today.

Please Log in or Create an account to join the conversation.

More
20 Aug 2016 15:54 #6 by fredparis
Hi,

At first, for this 05/08/2016,
I have 3 allocations (on 3 activities).
- Soutien => 0,25
- Recette => 0.25
- Etudes => 0.5
The sum is = 1 (day)
But after leaving and return
to this activity screen (#31)
soutien = 0.5
and so sum = 1,25
(my first post).
I have try to write another timesoutien = 0.25but the problem persists.soutien = 0.5
sum = 1,25
(my first post).
Today, I try this :- Etude => 0.25
- Soutien => 0.5 (no change)
- Sum = 1
After coming back to the screen :- Etude => 0.25
- Soutien => 0.75 !!!
- Sum = 1.25
Another test- Soutien => 0
- Sum = 0.75
After coming back to the screen :- Soutien => 0
- Sum = 0.75
Last input :- Soutien => 0.25
- Sum = 1
After coming back to the screen :- Soutien => 0.25
- Sum = 1

That is finally correct !!!
And now, the real work allocation screen remains correct !
It seems like I had to write and save a zero value (0) for Soutien allocation, before write the correct value...
It's the first time this problem occurs...

If this can help...
Fred

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.077 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.