[SOLVED] No control between dates (handled <= done <= closed) ?

More
20 Aug 2016 13:07 #1 by fredparis
Hi Babynus,

In the activity screen (and perhaps not only here), it seems there is no control between the three dates :
- handled = 01/08/2016
- done = 01/07/2016
- closed = 01/06/2016

So "done" can be a day before "handled" and after "closed".
Illogical and nonsense, isn't it ?

I agree that any input action may be carefully done, but anybody can do a mistake or a bad click and select a bad month or a bad year...
So, if this test can be in a future version of ProjeQtOr...

Thanks,
Fred

Please Log in or Create an account to join the conversation.

More
20 Aug 2016 13:23 #2 by babynus
Yes, possibly control handled date <= done date could be added
others are no so simple, because an item (activity or else) could be closed without handled and done are set.

But this is no major issue if you let these data be set by status change...

By the way, request recorded as Ticket 2276

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: fredparis

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.