ProjeQtOr free project management software - [v6.0.1 acceptance review] - milestone fix - ProjeQtOr
 
 

[v6.0.1 acceptance review] - milestone fix

More
30 Nov 2016 19:04 #1 by VERGES
in the real project life , projects begin whereas we are in advance phase.

we don't have the possibility in this version to fix a "reference planning" before the "today date"...

is it possible to choose a date of the refernce planning in order, for example" to fix a reference planning for the T0 of the project...

This action permits to fix the fist miletone date at T0 of the project even if we have already begined the project

Please Log in or Create an account to join the conversation.

More
01 Dec 2016 12:06 #2 by babynus
Hi,

This is a very specific use case.
To take this into account we propose to be able to enter baseline date as long as no baseline already exist for the project.
Hope this fits the need.

Request is Ticket #2405

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
08 Dec 2016 16:24 #3 by VERGES
[v6.0.3 acceptance review] - OK, thanks you. Now is possible to tag a past baseline.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.024 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.