Cost Evaluation in Save Assignment

More
13 Dec 2016 09:54 #1 by antonio.grr
Hi.
In saveAssignment.php I see

foreach ($wkList as $wk) {
$wk->dailyCost=$cost;
$wk->dailyCost=$cost*$wk->work;
$wk->save();
}

Maybe

foreach ($wkList as $wk) {
$wk->dailyCost=$cost;
$wk->cost=$cost*$wk->work;
$wk->save();
}

Best regards.

Please Log in or Create an account to join the conversation.

More
13 Dec 2016 10:36 #2 by babynus
You're right ;)

Fortunately this issue occurs only in very specific use case : change assignment which changes daily cost from zero to non zero value.

Code fixed, will be included in next patch/version.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.028 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.