We have a critical issue about "planned date" milestone:
- When the milestone is "fixed" and validated or delivered:
The "planned date" shall be the same date than the "real date" when "done" is checked.
Now, the "planned date" corresponds to the "validated date" when the milestone is fixed.
- When the milestone is "floating" and validated or delivered :
The "planned date" shall be the same date than the "real date" when "done" is checked. During planification of the projet, even if the milestone is done, the planned date is updated and does not corespond to the real date. See an example attached.
To summarize, for all milestones, if "done" is checked ==>planned date" = "real date".
Planned date (for milstones and for activities) is always result of latest planning calculation.
And when real is set, value is not planned any more.
This explains why planned date is always "last planned" date and is not equal to real.
Hello,
I've checked with the Project Manager and we always have this issue. You can find attached this problem.
In this example the real is set. (28/02/2017). The value is unfornutaly planned (01/03/2017).
It is a problem for the 45° curve too. Because, it is not the real date which is displayed but the false planned date. It is a big issue about reporting for ou client.
Also, concerning the 45° curve, when the real date is set before the planned date, the 45° cuve should be displayed the real date and not the planned date.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.