We have an issue on a project about the display of "reassessed" workload.
On this project (cf. capture attached, the "reaseessed" workload is : 105.75).
The S curve displays the "assigned" workload rather than the "reassessed" workload (cf. capture attached). There is an issue on the "Coût réel du travail effectué (prévu)" curve.
There may be a difference with reassessed work (on project) and S-curve :
- the reassessed work automatically takes into account actualized left work
- the S-curve takes into account work planned, day by day.
So if left work has been changed since last planning calculation, there will be a difference.
I cannot see wource of issue, and it's difficult to analyse without reproducing.
What is weird is that S-Curve stops on April 10th, although it should continue up to April 19th (planned end date).
Could you provide us with an anomized dump of your database to let us analyse ? (contact le through mail)
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.