[v6.0.1 acceptance review] - S curve validate planning

More
03 Mar 2017 18:54 #1 by VERGES
hi,

Two datas for this S curve:

1. The "budgeted cost of work scheduled" curve ("work days" axe) is calculated on the duration of the project between planned "start date " and "end date".

==>I think is false because we have to calculate at the begining of the project the repartition of the "reassessed" workload .


2. The "budgeted cost of work scheduled" curve (date axe) is calculated on the planned "end date".

==>When we establish the reference planning (in order to display the budgeted cost of work scheduled), we don't have all ressources available to assigned to the project and to the activity (task). The tool shall give the opportunity to "plan the planning" in the same way to "validate the planning". That means to save validated date to planned date. When we planned the project, sometimes we don't need to use the "automatic calculation" function in order to have the same planning than the planning shown to the customer (at T0 of the project).

Please Log in or Create an account to join the conversation.

More
04 Mar 2017 20:47 #2 by babynus
The "budgeted cost of work scheduled" is exactely the baseline saved (the one selected to display the report).
So it may not take into account reassessed work that was not known when baseline was saved.

About saving validated to planned, this would not change anything on S-Curve, as it needs exact planning day by day, to produce curves.
Otherwise we would have straight lines.
As ProjeQtOr is effort driven, there is no way to get planning other than assigning resources to tasks.
Qo if you don't know yet which resource will work, possibly you should use "virtual" resources to get first planning.
This solution has the advantage that when the real resource is selected, you just have to "switch" allocation to project from "virtual" to "real".

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.032 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.