is there a possibility to set the progress planning for some activites standardly on “must not start before validated date”?
We tried to change the default planning mode of the activity type but when we planned new activities with this type, the planning Progress is still “as soon as possible”. But we need to fill in the validated start date.
Strangely enough after the change we had some problems with other activity types (which we didn’t change). It seems the acitivities also are planned with “must not start before validated date”. We cann’t make new activities or copy projects without a validated start date.
we updated to Version V6.3.5.
Now I changed the 'Default planning mode' at one activty to 'must not start before validated date'. But now we still have the Problem that after that all Projects which doesn't (!) have this activity in the plan want's to have a validated start date. Can you explain me why? We have some Projects which don't have an validated start date and shall start as soon as possible and some which have a validated start date. I thougt I can manage this with the different types of activites?!
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.